Rankweil
Pfäfersweg

Price advantage: Your dream apartment at a reduced purchase price
Condominiums in a quiet area on the edge of the forest
Apartments already ready for occupancy or in shell construction

Time for change - including the price

Benefit now from the price advantage of the already completed apartments in a wonderful location in Rankweil. High-quality living at a reduced price. Here you can look forward to dream homes in luxury shell construction and thus space for your individual wishes. Arrange a viewing now!

Close to nature with good infrastructure


The four residential buildings on Pfäfersweg are impressive, among other things, due to the small number of apartments, generous outdoor areas in the form of private gardens or covered terraces and spacious open spaces between the buildings. In the living rooms, floor-to-ceiling windows offer a view of the wonderfully green surroundings. The open-plan living and kitchen areas are optimally oriented towards the terrace or garden. Panoramic glazing creates a connection to the outside and creates a bright living atmosphere.

The different materializations of the facade form a gentle contrast. A facade cladding made of wood with vertical slats is used on the ground floor and 1st upper floor, while the top floor is clad with colored sheet metal. The shared underground car park, cellar compartments, bicycle storage rooms and a children's playground complete the comfortable living concept.

Choose
your dream apartment

Here you can find all apartments at a glance or filtered according to your preferences. You can get details and floor plans by clicking on the respective element. By the way: You can save your apartment selection at any time for later and call it up in your watch list.

House
A B C D
Floors
Ground 1st Top
Number of rooms
2 3 4
Living space
50 m² 120 m²
Price
310000 970000
TOP (4) House Room floor Living space WBF Price Save
C07 House: C 3 Top 68.15 m² Residential construction funding 459000
C04 House: C 3 1st 69.78 m² Residential construction funding 429000
B06 House: B 4 Top 118.41 m² 899000
A07 House: A 3 Top 68.61 m² Residential construction funding 449000

Unfortunately, no apartments are available

Object name
House | Floor | Top
Project name
Living space
  • Element
Apartment purchase price
plus additional costs
Monthly installment from
Investor: Purchase price apartment
plus VAT and ancillary costs
Parking space purchase price
plus additional costs
Investor: Purchase price TG parking space
plus VAT and ancillary costs
Operating costs

Quiet idyll with
ideal infrastructure


Rankweil offers a diverse quality of life with an active community life, quiet residential areas, leisure activities in nature and optimal transport connections and infrastructure. Just a few meters from your new home, you can access a widely branched network of hiking and cycling trails. For shorter after-work tours, a hike to the „Hoher Sattel“ is ideal. Schafplatz Rankweil is also not far away – a public square with barbecue areas, a water playground and a large meadow for playing and relaxing in quiet nature.

Several bathing lakes, such as the Paspels lakes, can be reached in about 15 minutes by bicycle. From Pfäfersweg it is about a 10-minute walk to the center of the Rankweil community, where the Vinomna Center shopping center, various shops, cafes, restaurants, doctors and a pharmacy can be found. You can reach the Passage 22 shopping center with other restaurants and service providers in 10 minutes by bike. It is only about 3 minutes to the A14 motorway entrance. Here, too, the location on Pfäfersweg is an advantage: by car it takes about 10 minutes to get to Feldkirch city center and 15 minutes to the Dornbirn-West exit.

To display the Google Maps map, loading the script must be allowed.
  • Vinomna Center shopping center within walking distance
  • 4 minutes on foot to the nearest bus stop, 11 minutes to Rankweil train station
  • 15 minutes by bike to Brederis bathing lakes, 2 minutes to Schafplatz
  • Kindergarten, elementary and secondary school, HTL/HLW in the immediate vicinity

Features


ZIMA basic equipment – high-quality, clear design
Bathrooms and WC rooms are furnished with modern, high-quality bathroom and sanitary equipment from well-known manufacturers. Simple, elegant design combines with high-quality materials such as glass, metal and porcelain stoneware.

The ZIMA basic features focus on a clear design language and first-class workmanship. With elegant wooden parquet flooring, a lively and warm living atmosphere is created, which gives your living spaces a special touch. Proven laying methods and the high quality of the raw material are just as much in focus as consistent sound insulation and a harmonious overall concept in your home.

CONSTRUCTION PROGRESS

We would be happy to keep you up to date! Enter your email address and we will send you regular construction updates.

August 2025

We would like to present the photos of the completed project. The lovingly designed outdoor areas are now in full bloom in the summer. The first residents were able to move into their apartments in the spring. We hope you enjoy your new home! There are currently still 3-room apartments and a penthouse available.
February 2025

The final painting work, door installation and final work on the outdoor facilities are currently underway in Pfäfersweg.
February 2025

In House C, the parquet flooring and door installation are underway. In House D, the filling and priming work is being carried out, the roof is being greened and paving work is taking place.
December 2024

In Houses A and B, the final clean-up and cleaning work is taking place. Work is currently being carried out on the main roof of House C, and the interior railings are being installed inside. Tiling work, work on the main roof and on the outdoor facilities are underway in and around House D.
December 2024

Paving work is underway on Houses A and B and asphalt preparation is in progress. Humus is also being applied. Tiling work is currently being carried out in House C and the stairwell is being tiled and facade work is being carried out in House D.
November 2024

Houses A+B: Painting work, completion by electricians, cleaning, facade nearing completion | House C: Heating up the screed, filling and plastering work, dismantling the scaffolding | House D: Screed laid, filling and plastering work, facade work | General: Paving work
October 2024

In Houses A and B, painting and completion work by electricians and plumbers are currently taking place. Facade work is underway in and on House C, the screed has been installed and filling work is taking place. In House D, the floor insulation is being laid and work is also being carried out on the facades. Civil engineering work is also generally underway.
October 2024

Painting and completion work is taking place in Houses A and B. Underfloor heating is being installed and facade work is underway in House C. In House D, however, drywall and facade work is being carried out. Meanwhile, work is also being carried out on the outdoor facilities and the basement compartments are being installed.
September 2024

In September, the parquet flooring was laid and the doors were installed in Houses A and B. In House C, the drywall partitions were erected, the rough installations were completed and the plasterboard walls were closed. In House D, the interior plastering work and the rough installations were started and the facade was insulated. In addition, there was … Learn more
August 2024

At the end of August, the scaffolding was removed from House A and sealing work was carried out. The apartments in House B were primed. Work on the facades, drywall and rough installations has started on House C. The windows were installed and the interior plastering work took place in House D.
August 2024

In August, facade and tiling work took place in House A. The apartments in House B were primed. In House C, the windows were installed, the drywall and plastering work was carried out in August, and the windows were delivered and the ceiling was filled in House D.
July 2024

– House A: Stairwell tiled and railings installed, start of aluminum facade, terrace slabs laid
– House B: Outer aluminum facade completed, scaffolding removed, terrace slabs laid, door frames painted, painter's covering work
– House C: Temporary roof torched, window installation
– House D: Torch work on temporary roof
July 2024

– House A: Screed drying time
– House B: Tiling work in bathrooms and stairwell completed, work on the main roof
– House C: Grinding and filling the ceiling
– House D: Walls top floor
July 2024

– House A: Wooden facade completed, ceiling filling in progress, balconies sealed
– House B: Ceilings and walls filled, tiling work started, aluminum facade in progress
– House C: Shell completed
– House D: Installation work on the ceiling above the upper floor
June 2024

Facade work and screed installation are taking place in and on House A. Facade and filling work is also underway on House B. In House C, on the other hand, the installation work on the top ceiling is in full swing. Work is being carried out on the walls of the 1st floor in House D.
June 2024

– House A: Substructure and insulation of the facade completed, underfloor heating laid, plastering work
– House B: Substructure and insulation of the facade completed, ceiling filling, balconies sealed
– House C: Walls top floor
– House D: Ceiling above ground floor
– General: Boreholes for geothermal probes
May 2024

In House A, the rough installations have been completed and the walls have been closed, and the screed has been laid in House B. The ceiling of the 1st floor is currently being formworked on House C and work is underway on the walls of the ground floor on House D.


May 2024

– House A: Rough installations by electricians and plumbers
– House B: Underfloor heating laid, facade insulated
– House C: Walls 1st floor
– House D: Basement ceiling concreted
April 2024

Interior plastering is currently in progress in House A and drywall work has begun. In House B, the rough installations have been completed, the drywaller is closing the walls, the elevator is installed and the facade work has started. Work is underway on the ceiling above the ground floor in House C and on the base plate in House D.
April 2024

The following work is currently taking place in Rankweil:

House A = Window installation, preparatory work for interior plastering, plasterboard stored
House B = Rough installations, structural waterproofing
House C and D = Structural work, backfilling and sewer work
March 2024

The work on the construction site in Rankweil is progressing according to plan. House A: Stripping work, window delivery. House B: Window installation completed, plastering work started, drywall work started. House C: Structural work, first basement ceiling concreted. House D: Structural work, base plate concreted.
February 2024

In Rankweil, the last ceiling is being formworked on House A. The shell of House B has already been completed – stripping and clean-up work is taking place here and the temporary roof is being torched. Work is underway on the excavation pit shoring, the foundations and the insulation on Houses C and D.
February 2024

The construction work in Rankweil is progressing according to plan. The walls are being erected in the top floor of House A. The ceiling is already being built in the top floor of House B. The excavation of the building pit is taking place at Houses C and D.
January 2024

The formwork for the ceiling above the 1st floor is taking place on House A – concreting will take place on Friday. Work is underway on the walls of the top floor on House B, while excavation has started for Houses C and D.
December 2023

– House A: Concreting walls 1st floor
– House B: Ceiling above 1st floor concreted

The precast stairs will be installed in both houses today before the construction team goes on vacation the day after tomorrow.
December 2023

In Rankweil, the ceiling above the ground floor will be concreted on House A from tomorrow. The walls on the 1st upper floor have been completed on House B. The ceiling above the 1st floor is currently being formworked.
November 2023

The following work is currently underway on houses A and B: Insulation of the basement, laying of house connections, backfilling work, basement ceiling finished, walls of house B nearing completion.
October 2023

This week, the last basement walls will be concreted, followed by the last basement ceiling at house A. The first ground floor walls of house B will also be concreted.
October 2023

The basement walls of house B are finished, and those of house A are currently in progress. The basement ceiling between houses A and B is shuttered, reinforcement work is taking place, and concreting will be done at the end of the week.
October 2023

Tomorrow (03.10.) the last floor slab section will be concreted. The basement walls of house B are nearing completion. Shuttering work on the first ceiling section is starting.
September 2023

The first part of the floor slab has been concreted. This week, the 2nd section of the floor slab and the first basement walls will be concreted.
August 2023

The excavation and excavation pit shoring are complete. Work has started on the foundations, main pipes, and insulation under the floor slab.
July 2023

Construction start for the Pfäfersweg project! This week, the infrastructure lines were relocated. Next week, the construction road and construction site equipment will be installed so that excavation for houses A and B can start the following week.