Green Wave
July 2026
All interior partition walls in the apartments have been completed. Electrical and plumbing work in the apartments is currently underway, as is the interior plastering. At the same time , insulation has been installed on most of the facade, and the exterior plastering has been completed. The concrete parapets on the upper floors have been completed, and waterproofing work on the roof is currently underway.